| Fundamental Work Equation | W=E×T⟺E=TW⟺T=EW Core linear relationship linking total output, rate of work, and duration. |
|---|
| LCM Total Work Definition | W=LCM(T1,T2,…,Tn) Transforms fractional work rates into clean, non-negative integers. |
|---|
| Two-Worker Shortcut | TAB=TA+TBTA×TB Harmonic product-over-sum for two parallel workers. |
|---|
| Virtual Work Shortcut | Ttotal=∑EWactual+Edeparting×k For a worker departing k days before completion, add virtual work and divide by combined efficiency. |
|---|
| Pairwise Cyclic Efficiency Sum | EA+EB+EC=2EA+B+EB+C+EC+A Divides sum of pairwise combinations by 2 to isolate individual contributions. |
|---|
| Master MDH Variation Chain | W1M1D1H1E1=W2M2D2H2E2 Universal proportionality relation connecting workforce, time, efficiency, and physical output. |
|---|
| Demographic Equivalence Efficiency | aEM=bEW=cEC⟹EM:EW:EC=a1:b1:c1 Transforms mixed gender/age workforces into unified efficiency units. |
|---|
| Contractor Remaining Work Balance | Mnew=M1×DremDpast×WdoneWrem Directly calculates required final team size from the audit date onwards. |
|---|
| Garrison Ration Balance | M1×D1=M2×D2 For constant total food supply, worker headcount is inversely proportional to surviving days. |
|---|
| Cycle Work Output | Wcycle=∑i=1nEi Total work completed in one full cyclic rotation of n workers. |
|---|
| Number of Full Cycles | k=⌊WcycleWtotal⌋ Integer floor of complete cycles before remainder handling. |
|---|
| Residual Time Division | Tresidual=EactiveR Fraction of a day needed by the active worker to finish residual units R. |
|---|