CAT Time and Work: Concepts and Formulas

7 concepts for CAT Time and Work (Arithmetic), from basics to CAT-level shortcuts.

  1. Work Rate, Efficiency Units & The LCM Method
    Master the foundational Work = Rate × Time equation, transition from fractional unitary arithmetic to the integer LCM efficiency method, and seamlessly solve segmented timelines with staggered…
  2. Group Work & The Man-Day-Hour Variation Chain (MDHE / W)
    Master the unified Man-Day-Hour (MDH) proportionality chain, workforce demographic equivalences (Men, Women, Children), and tactical contractor renegotiations when deadlines are threatened.
  3. Alternate Working Days & Cyclic Step Sequencing
    Master cyclic work scheduling where agents work on alternating days, compute complete repeating blocks, handle delicate final-day remainders, and analyze sensitivity to the starting worker.
  4. Wage Distribution & Piecework Compensation
    Master the fundamental economic rule of piecework compensation: wages are distributed strictly in proportion to total work delivered, not merely days spent on site.
  5. Pipes & Cisterns: Inlets, Outlets & Drainage Leaks
    Master the hydrodynamic model of reservoirs, positive inlet filling rates, negative outlet emptying rates, concealed bottom leaks, and elevated leaks positioned at fractional tank heights.
  6. Practice Set 1: Foundation & Conceptual Drill
    Comprehensive 25-question practice drill mirroring Chapter 5 Exercise 1 with fresh thematic scenarios and mathematically verified solutions.
  7. Practice Set 2: Advanced & CAT Exam-Level Drill
    Rigorous 25-question advanced drill mirroring Chapter 5 Exercise 2 with multi-variable constraints and authentic CAT-level traps.

Key formulas

Fundamental Work Equation

W=E×T  ⟺  E=WT  ⟺  T=WEW = E \times T \iff E = \frac{W}{T} \iff T = \frac{W}{E}

Core linear relationship linking total output, rate of work, and duration.
LCM Total Work Definition

W=LCM(T1,T2,…,Tn)W = \text{LCM}(T_1, T_2, \dots, T_n)

Transforms fractional work rates into clean, non-negative integers.
Two-Worker Shortcut

TAB=TA×TBTA+TBT_{AB} = \frac{T_A \times T_B}{T_A + T_B}

Harmonic product-over-sum for two parallel workers.
Virtual Work Shortcut

Ttotal=Wactual+Edeparting×k∑ET_{\text{total}} = \frac{W_{\text{actual}} + E_{\text{departing}} \times k}{\sum E}

For a worker departing k days before completion, add virtual work and divide by combined efficiency.
Pairwise Cyclic Efficiency Sum

EA+EB+EC=EA+B+EB+C+EC+A2E_A + E_B + E_C = \frac{E_{A+B} + E_{B+C} + E_{C+A}}{2}

Divides sum of pairwise combinations by 2 to isolate individual contributions.
Master MDH Variation Chain

M1D1H1E1W1=M2D2H2E2W2\frac{M_1 D_1 H_1 E_1}{W_1} = \frac{M_2 D_2 H_2 E_2}{W_2}

Universal proportionality relation connecting workforce, time, efficiency, and physical output.
Demographic Equivalence Efficiency

aEM=bEW=cEC  ⟹  EM:EW:EC=1a:1b:1ca E_M = b E_W = c E_C \implies E_M : E_W : E_C = \frac{1}{a} : \frac{1}{b} : \frac{1}{c}

Transforms mixed gender/age workforces into unified efficiency units.
Contractor Remaining Work Balance

Mnew=M1×DpastDrem×WremWdoneM_{\text{new}} = M_1 \times \frac{D_{\text{past}}}{D_{\text{rem}}} \times \frac{W_{\text{rem}}}{W_{\text{done}}}

Directly calculates required final team size from the audit date onwards.
Garrison Ration Balance

M1×D1=M2×D2M_1 \times D_1 = M_2 \times D_2

For constant total food supply, worker headcount is inversely proportional to surviving days.
Cycle Work Output

Wcycle=∑i=1nEiW_{\text{cycle}} = \sum_{i=1}^n E_i

Total work completed in one full cyclic rotation of n workers.
Number of Full Cycles

k=⌊WtotalWcycle⌋k = \left\lfloor \frac{W_{\text{total}}}{W_{\text{cycle}}} \right\rfloor

Integer floor of complete cycles before remainder handling.
Residual Time Division

Tresidual=REactiveT_{\text{residual}} = \frac{R}{E_{\text{active}}}

Fraction of a day needed by the active worker to finish residual units R.

Previous year questions

Recent CAT questions on Time and Work

  1. CAT 2025 Slot 1 Quant Q16
    Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They charge Rs…
  2. CAT 2025 Slot 2 Quant Q10
    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start together…
  3. CAT 2025 Slot 3 Quant Q7
    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a team is…
  4. CAT 2025 Slot 3 Quant Q13
    The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be filled up…
  5. CAT 2024 Slot 1 Quant Q21
    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5…
  6. CAT 2024 Slot 2 Quant Q7
    Amal and Vimal together can complete a task in 150 days, while Vimal and Sunil together can complete the same task in…
  7. CAT 2024 Slot 3 Quant Q20
    Sam can complete a job in 20 days when working alone. Mohit is twice as fast as Sam and thrice as fast as Ayna is the…
  8. CAT 2023 Slot 1 Quant Q16
    The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes…