CAT 2024 Slot 1 Quant Q21
- Quantitative Aptitude
- Arithmetic › Time & Work
- Medium
- Type in the answer (TITA)
- CAT_2024_SLOT1_QA_Q21
Question 21
Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
6
Solution
-
Work ratio: Renu needs 60 hrs, Seema needs 40 hrs. Efficiency ratio Renu:Seema = 40:60 = 2:3.
-
Daily work ratio: Renu (2 hrs 2 eff = 4 units), Seema (4 hrs 3 eff = 12 units).
-
Total work expressed in terms of Seema's days : Renu works days. Total units = .
-
Total work requires units.
-
.
Detailed explanation
Concept: Work and Time.
-
Renu takes 15 days 4 hours/day = 60 total hours.
-
Seema takes 8 days 5 hours/day = 40 total hours.
-
Let total work be LCM(60, 40) = 120 units.
-
Renu's efficiency = units/hour.
-
Seema's efficiency = units/hour.
-
Renu now works 2 hours/day, so Seema works double that, which is 4 hours/day.
-
Seema works for days, so Renu works for days.
-
Renu's total work = units.
-
Seema's total work = units.
-
Total work = .
-
Equating to total work: days.
Practise similar questions
Practice 1 CAT_2024_SLOT1_QA_Q21_SQ01
Amit would take 10 days working 6 hours per day to complete a software module, whereas Bhavna would take 6 days working 5 hours per day to complete the same module. They decide to work together to complete this module. Bhavna agrees to work for double the number of hours per day as Amit, while Amit agrees to work for double the number of days as Bhavna. If Amit works 2 hours per day, then the number of days Bhavna will work, is
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
5
Solution
-
Work ratio: Amit requires 60 hours, Bhavna requires 30 hours. Total work = 60 units.
-
Hourly efficiencies: Amit = 1 unit/hr, Bhavna = 2 units/hr.
-
Daily rates under new schedule: Amit (2 hrs 1 = 2 units/day), Bhavna (4 hrs 2 = 8 units/day).
-
Days allocation: Bhavna works days, Amit works days.
-
Total work equation: .
Practice 2 CAT_2024_SLOT1_QA_Q21_SQ02
Rajesh would take 20 days working 6 hours per day to weave a traditional carpet, whereas Suresh would take 10 days working 8 hours per day to weave the same carpet. They decide to work together to complete this carpet. Suresh agrees to work for double the number of hours per day as Rajesh, while Rajesh agrees to work for double the number of days as Suresh. If Rajesh works 3 hours per day, then the number of days Suresh will work, is
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
8
Solution
-
Work required: Rajesh needs 120 hours, Suresh needs 80 hours. Total work = LCM(120, 80) = 240 units.
-
Hourly efficiencies: Rajesh = 2 units/hr, Suresh = 3 units/hr.
-
Daily output: Rajesh works 3 hrs 2 = 6 units/day; Suresh works 6 hrs 3 = 18 units/day.
-
Total work equation: Rajesh works days and Suresh works days .
-
Solving for : .
Time & Work questions from other CAT papers
- CAT 2025 Slot 1 Quant Q16
- CAT 2025 Slot 2 Quant Q10
- CAT 2025 Slot 3 Quant Q7
- CAT 2025 Slot 3 Quant Q13
- CAT 2023 Slot 1 Quant Q16
Practise this question with timing, notes and your mistake notebook.
Practise in PrepSoc