CAT 2024 Slot 1 Quant Q21

  • Quantitative Aptitude
  • Arithmetic › Time & Work
  • Medium
  • Type in the answer (TITA)
  • CAT_2024_SLOT1_QA_Q21

Question 21

Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is

Type-in-the-answer (TITA) question: no options are given; enter the value.

Answer this question Opens in practice mode, free, no sign-in.

Show answer and solution

Answer:

6

Solution

  • Work ratio: Renu needs 60 hrs, Seema needs 40 hrs. Efficiency ratio Renu:Seema = 40:60 = 2:3.

  • Daily work ratio: Renu (2 hrs ×\times 2 eff = 4 units), Seema (4 hrs ×\times 3 eff = 12 units).

  • Total work expressed in terms of Seema's days xx: Renu works 2x2x days. Total units = 2x(4)+x(12)=20x2x(4) + x(12) = 20x.

  • Total work requires 60×2=12060 \times 2 = 120 units.

  • 20x=120  ⟹  x=620x = 120 \implies x = 6.

Detailed explanation

Concept: Work and Time.

  1. Renu takes 15 days ×\times 4 hours/day = 60 total hours.

  2. Seema takes 8 days ×\times 5 hours/day = 40 total hours.

  3. Let total work be LCM(60, 40) = 120 units.

  4. Renu's efficiency = 120/60=2120 / 60 = 2 units/hour.

  5. Seema's efficiency = 120/40=3120 / 40 = 3 units/hour.

  6. Renu now works 2 hours/day, so Seema works double that, which is 4 hours/day.

  7. Seema works for xx days, so Renu works for 2x2x days.

  8. Renu's total work = 2x days×2 hrs/day×2 units/hr=8x2x \text{ days} \times 2 \text{ hrs/day} \times 2 \text{ units/hr} = 8x units.

  9. Seema's total work = x days×4 hrs/day×3 units/hr=12xx \text{ days} \times 4 \text{ hrs/day} \times 3 \text{ units/hr} = 12x units.

  10. Total work = 8x+12x=20x8x + 12x = 20x.

  11. Equating to total work: 20x=120  ⟹  x=620x = 120 \implies x = 6 days.

Practise similar questions

Practice 1 CAT_2024_SLOT1_QA_Q21_SQ01

Amit would take 10 days working 6 hours per day to complete a software module, whereas Bhavna would take 6 days working 5 hours per day to complete the same module. They decide to work together to complete this module. Bhavna agrees to work for double the number of hours per day as Amit, while Amit agrees to work for double the number of days as Bhavna. If Amit works 2 hours per day, then the number of days Bhavna will work, is

Type-in-the-answer (TITA) question: no options are given; enter the value.

Show answer and solution

Answer:

5

Solution

  • Work ratio: Amit requires 60 hours, Bhavna requires 30 hours. Total work = 60 units.

  • Hourly efficiencies: Amit = 1 unit/hr, Bhavna = 2 units/hr.

  • Daily rates under new schedule: Amit (2 hrs ×\times 1 = 2 units/day), Bhavna (4 hrs ×\times 2 = 8 units/day).

  • Days allocation: Bhavna works dd days, Amit works 2d2d days.

  • Total work equation: 2d(2)+d(8)=12d=60  ⟹  d=52d(2) + d(8) = 12d = 60 \implies d = 5.

Practice 2 CAT_2024_SLOT1_QA_Q21_SQ02

Rajesh would take 20 days working 6 hours per day to weave a traditional carpet, whereas Suresh would take 10 days working 8 hours per day to weave the same carpet. They decide to work together to complete this carpet. Suresh agrees to work for double the number of hours per day as Rajesh, while Rajesh agrees to work for double the number of days as Suresh. If Rajesh works 3 hours per day, then the number of days Suresh will work, is

Type-in-the-answer (TITA) question: no options are given; enter the value.

Show answer and solution

Answer:

8

Solution

  • Work required: Rajesh needs 120 hours, Suresh needs 80 hours. Total work = LCM(120, 80) = 240 units.

  • Hourly efficiencies: Rajesh = 2 units/hr, Suresh = 3 units/hr.

  • Daily output: Rajesh works 3 hrs ×\times 2 = 6 units/day; Suresh works 6 hrs ×\times 3 = 18 units/day.

  • Total work equation: Rajesh works 2d2d days and Suresh works dd days   ⟹  2d(6)+d(18)=30d=240\implies 2d(6) + d(18) = 30d = 240.

  • Solving for dd: d=240/30=8d = 240 / 30 = 8.

Time & Work questions from other CAT papers

  1. CAT 2025 Slot 1 Quant Q16
    Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They…
  2. CAT 2025 Slot 2 Quant Q10
    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start…
  3. CAT 2025 Slot 3 Quant Q7
    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a…
  4. CAT 2025 Slot 3 Quant Q13
    The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be…
  5. CAT 2023 Slot 1 Quant Q16
    The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression.…

Practise this question with timing, notes and your mistake notebook.

Practise in PrepSoc