Question 16
Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They charge Rs 2160, Rs 2400, and Rs 2160 per day, respectively, even if they are employed for a partial day. On any given day, any of the workers may or may not be employed to work. If the task needs to be completed in 10 days or less, then the minimum possible amount, in rupees, required to be paid for the entire task is
Show answer and solution
Answer: (A)
38400
Solution
-
Identify Cost Efficiency: Full-task costs are Tarun (32.4k) < Varun (50.4k) < Arun (51.8k).
-
Maximize Cheapest Labor: Employ Tarun for the maximum 10 days Work done . Cost .
-
Assign Remainder: Remaining goes to the next cheapest, Varun. Time days. Cost .
-
Total Minimum Cost: .
Detailed explanation
Concept: [Work and Wages Optimization]
- Find the cost of completing the entire task for each worker alone:
-
Arun:
-
Varun:
-
Tarun:
-
Rank workers by cost efficiency (cheapest first): Tarun, Varun, Arun.
-
To minimize cost while finishing in days, maximize Tarun's working days. Assign Tarun for 10 days.
-
Work completed by Tarun .
-
Remaining work .
-
Assign the next cheapest worker (Varun) to the remaining work. Days needed by Varun days. This fits within the 10-day limit if he works concurrently.
-
Total minimum cost .
Practise similar questions
Practice 1 CAT_2025_SLOT1_QA_Q16_SQ01
Dev, Aman and Kabir, if working alone, can complete a software project in 30, 25, and 20 days, respectively. They charge Rs 1700, Rs 1920, and Rs 1800 per day, respectively, even if they are employed for a partial day. On any given day, any of the programmers may or may not be employed to work. If the project needs to be completed in 12 days or less, then the minimum possible amount, in rupees, required to be paid for the entire project is
Show answer and solution
Answer: (A)
40800
Solution
-
Compare Total Solo Costs: Kabir () < Aman () < Dev ().
-
Maximize Cheapest Worker: Employ Kabir for the full 12-day deadline Work done , Cost .
-
Assign Remainder to Next Cheapest: Remaining goes to Aman Days needed days (fits ). Cost .
-
Total Minimum Cost: . Matches Option 1.
Practice 2 CAT_2025_SLOT1_QA_Q16_SQ02
Rohan, Sohan and Mohan, if working alone, can landscape a garden in 24, 20, and 16 days, respectively. They charge Rs 2200, Rs 2400, and Rs 2500 per day, respectively, even if they are employed for a partial day. On any given day, any of the workers may or may not be employed to work. If the landscaping needs to be completed in 12 days or less, then the minimum possible amount, in rupees, required to be paid for the entire work is
Show answer and solution
Answer: (B)
42000
Solution
-
Compare Total Solo Costs: Mohan () < Sohan () < Rohan ().
-
Maximize Cheapest Worker: Employ Mohan for 12 days Work done , Cost .
-
Assign Remainder to Next Cheapest: Remaining assigned to Sohan Days needed days (fits ). Cost .
-
Total Minimum Cost: . Matches Option 2.
Time & Work questions from other CAT papers
- CAT 2024 Slot 1 Quant Q21
- CAT 2024 Slot 2 Quant Q7
- CAT 2024 Slot 3 Quant Q20
- CAT 2023 Slot 1 Quant Q16
- CAT 2023 Slot 2 Quant Q8
Practise this question with timing, notes and your mistake notebook.
Practise in PrepSoc