Question 16

Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They charge Rs 2160, Rs 2400, and Rs 2160 per day, respectively, even if they are employed for a partial day. On any given day, any of the workers may or may not be employed to work. If the task needs to be completed in 10 days or less, then the minimum possible amount, in rupees, required to be paid for the entire task is

  1. A

    38400

    Answer A in PrepSoc practice
  2. B

    38880

    Answer B in PrepSoc practice
  3. C

    34400

    Answer C in PrepSoc practice
  4. D

    47040

    Answer D in PrepSoc practice

Answer this questionOr tap an option. Opens in practice mode, free, no sign-in.

Show answer and solution

Answer: (A)

38400

Solution

  • Identify Cost Efficiency: Full-task costs are Tarun (32.4k) < Varun (50.4k) < Arun (51.8k).

  • Maximize Cheapest Labor: Employ Tarun for the maximum 10 days →\rightarrow Work done =1015=23= \frac{10}{15} = \frac{2}{3}. Cost =21600= 21600.

  • Assign Remainder: Remaining 13\frac{1}{3} goes to the next cheapest, Varun. Time =13×21=7= \frac{1}{3} \times 21 = 7 days. Cost =7×2400=16800= 7 \times 2400 = 16800.

  • Total Minimum Cost: 21600+16800=3840021600 + 16800 = 38400.

Detailed explanation

Concept: [Work and Wages Optimization]

  1. Find the cost of completing the entire task for each worker alone:
  • Arun: 24×2160=5184024 \times 2160 = 51840

  • Varun: 21×2400=5040021 \times 2400 = 50400

  • Tarun: 15×2160=3240015 \times 2160 = 32400

  1. Rank workers by cost efficiency (cheapest first): Tarun, Varun, Arun.

  2. To minimize cost while finishing in ≤10\le 10 days, maximize Tarun's working days. Assign Tarun for 10 days.

  3. Work completed by Tarun =1015=23= \frac{10}{15} = \frac{2}{3}.

  4. Remaining work =1−23=13= 1 - \frac{2}{3} = \frac{1}{3}.

  5. Assign the next cheapest worker (Varun) to the remaining work. Days needed by Varun =13×21=7= \frac{1}{3} \times 21 = 7 days. This fits within the 10-day limit if he works concurrently.

  6. Total minimum cost =(10×2160)+(7×2400)=21600+16800=38400= (10 \times 2160) + (7 \times 2400) = 21600 + 16800 = 38400.

Practise similar questions

Practice 1 CAT_2025_SLOT1_QA_Q16_SQ01

Dev, Aman and Kabir, if working alone, can complete a software project in 30, 25, and 20 days, respectively. They charge Rs 1700, Rs 1920, and Rs 1800 per day, respectively, even if they are employed for a partial day. On any given day, any of the programmers may or may not be employed to work. If the project needs to be completed in 12 days or less, then the minimum possible amount, in rupees, required to be paid for the entire project is

  1. A

    40800

  2. B

    42000

  3. C

    39600

  4. D

    44400

Show answer and solution

Answer: (A)

40800

Solution

  • Compare Total Solo Costs: Kabir (20×1800=3600020 \times 1800 = 36000) < Aman (25×1920=4800025 \times 1920 = 48000) < Dev (30×1700=5100030 \times 1700 = 51000).

  • Maximize Cheapest Worker: Employ Kabir for the full 12-day deadline →\rightarrow Work done =1220=35= \frac{12}{20} = \frac{3}{5}, Cost =12×1800=21600= 12 \times 1800 = 21600.

  • Assign Remainder to Next Cheapest: Remaining 25\frac{2}{5} goes to Aman →\rightarrow Days needed =25×25=10= \frac{2}{5} \times 25 = 10 days (fits ≤12\le 12). Cost =10×1920=19200= 10 \times 1920 = 19200.

  • Total Minimum Cost: 21600+19200=4080021600 + 19200 = 40800. Matches Option 1.

Practice 2 CAT_2025_SLOT1_QA_Q16_SQ02

Rohan, Sohan and Mohan, if working alone, can landscape a garden in 24, 20, and 16 days, respectively. They charge Rs 2200, Rs 2400, and Rs 2500 per day, respectively, even if they are employed for a partial day. On any given day, any of the workers may or may not be employed to work. If the landscaping needs to be completed in 12 days or less, then the minimum possible amount, in rupees, required to be paid for the entire work is

  1. A

    44200

  2. B

    42000

  3. C

    43200

  4. D

    38000

Show answer and solution

Answer: (B)

42000

Solution

  • Compare Total Solo Costs: Mohan (16×2500=4000016 \times 2500 = 40000) < Sohan (20×2400=4800020 \times 2400 = 48000) < Rohan (24×2200=5280024 \times 2200 = 52800).

  • Maximize Cheapest Worker: Employ Mohan for 12 days →\rightarrow Work done =1216=34= \frac{12}{16} = \frac{3}{4}, Cost =12×2500=30000= 12 \times 2500 = 30000.

  • Assign Remainder to Next Cheapest: Remaining 14\frac{1}{4} assigned to Sohan →\rightarrow Days needed =14×20=5= \frac{1}{4} \times 20 = 5 days (fits ≤12\le 12). Cost =5×2400=12000= 5 \times 2400 = 12000.

  • Total Minimum Cost: 30000+12000=4200030000 + 12000 = 42000. Matches Option 2.

Time & Work questions from other CAT papers

  1. CAT 2024 Slot 1 Quant Q21
    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days…
  2. CAT 2024 Slot 2 Quant Q7
    Amal and Vimal together can complete a task in 150 days, while Vimal and Sunil together can complete the…
  3. CAT 2024 Slot 3 Quant Q20
    Sam can complete a job in 20 days when working alone. Mohit is twice as fast as Sam and thrice as fast as…
  4. CAT 2023 Slot 1 Quant Q16
    The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression.…
  5. CAT 2023 Slot 2 Quant Q8
    Pipes A and C are fill pipes while Pipe B is a drain pipe of a tank. Pipe B empties the full tank in one…

Practise this question with timing, notes and your mistake notebook.

Practise in PrepSoc