CAT 2025 Slot 3 Quant Q7

  • Quantitative Aptitude
  • Arithmetic › Time & Work
  • Medium
  • Multiple choice
  • CAT_2025_SLOT3_QA_Q07

Question 7

Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a team is equally productive. Working separately, teams A, B, and C can complete a certain job in 40 hours, 50 hours, and 4 hours, respectively. Two members from team A, three members from team B, and one member from team C together start the job, and the member from team C leaves after 23 hours. The number of additional member(s) from team B, that would be required to replace the member from team C, to finish the job in the next one hour, is

  1. A

    3

    Answer A in PrepSoc practice
  2. B

    1

    Answer B in PrepSoc practice
  3. C

    2

    Answer C in PrepSoc practice
  4. D

    4

    Answer D in PrepSoc practice

Answer this questionOr tap an option. Opens in practice mode, free, no sign-in.

Show answer and solution

Answer: (C)

2

Solution

  • Rates per member: A = 1200\frac{1}{200}, B = 1400\frac{1}{400}, C = 140\frac{1}{40}.

  • Make everything over 400: A = 2400\frac{2}{400}, B = 1400\frac{1}{400}, C = 10400\frac{10}{400}.

  • Current crew (2A + 3B + 1C) produces 4+3+10=174 + 3 + 10 = 17 units of work per hour out of 400 total units.

  • In 23 hours, they produce 23×17=39123 \times 17 = 391 units.

  • Remaining work = 400−391=9400 - 391 = 9 units to be done in 1 hour.

  • Current crew without C (2A + 3B) produces 4+3=74 + 3 = 7 units per hour.

  • We need 2 more units. Since each B member produces 1 unit per hour, we need exactly 2 additional members from B.

Detailed explanation

Concept: Work and Time (Rates)

  • Let the total work be W=1W = 1.

  • Rate of Team A (5 members) = 140\frac{1}{40} per hour.

  • Rate of one member of Team A = 140×5=1200\frac{1}{40 \times 5} = \frac{1}{200} per hour.

  • Rate of Team B (8 members) = 150\frac{1}{50} per hour.

  • Rate of one member of Team B = 150×8=1400\frac{1}{50 \times 8} = \frac{1}{400} per hour.

  • Rate of Team C (10 members) = 14\frac{1}{4} per hour.

  • Rate of one member of Team C = 14×10=140\frac{1}{4 \times 10} = \frac{1}{40} per hour.

  • Combined rate of 2 from A, 3 from B, and 1 from C:

  • Rinitial=2×1200+3×1400+1×140=4400+3400+10400=17400R_{initial} = 2 \times \frac{1}{200} + 3 \times \frac{1}{400} + 1 \times \frac{1}{40} = \frac{4}{400} + \frac{3}{400} + \frac{10}{400} = \frac{17}{400} per hour.

  • Work done in 23 hours = 23×17400=39140023 \times \frac{17}{400} = \frac{391}{400}.

  • Work remaining = 1−391400=94001 - \frac{391}{400} = \frac{9}{400}.

  • After C leaves, the rate of 2 from A and 3 from B is:

  • Rremaining=4400+3400=7400R_{remaining} = \frac{4}{400} + \frac{3}{400} = \frac{7}{400} per hour.

  • Let nn be the number of additional members from Team B. Each adds 1400\frac{1}{400} to the hourly rate.

  • We need the new rate to finish the remaining 9400\frac{9}{400} work in exactly 1 hour.

  • 7400+n400=9400\frac{7}{400} + \frac{n}{400} = \frac{9}{400}.

  • 7+n=9  ⟹  n=27 + n = 9 \implies n = 2.

  • The number of additional members from Team B is 2.

Practise similar questions

Practice 1 CAT_2025_SLOT3_QA_Q07_SQ01

Teams A, B, and C consist of four, six, and ten members, respectively, such that every member within a team is equally productive. Working separately, teams A, B, and C can complete a certain job in 30 hours, 30 hours, and 6 hours, respectively. Two members from team A, three members from team B, and one member from team C together start the job, and the member from team C leaves after 19 hours. The number of additional member(s) from team B, that would be required to replace the member from team C, to finish the job in the next one hour, is

  1. A

    2

  2. B

    3

  3. C

    4

  4. D

    1

Show answer and solution

Answer: (B)

3

Solution

  • Member-hours needed: Team A = 4×30=1204 \times 30 = 120, Team B = 6×30=1806 \times 30 = 180, Team C = 10×6=6010 \times 6 = 60.

  • Taking total work W=360W = 360 units, hourly rates per member are: A = 3, B = 2, C = 6.

  • Initial group (2A + 3B + 1C) produces 2(3)+3(2)+6=182(3) + 3(2) + 6 = 18 units/hr.

  • Work done in 19 hours =19×18=342= 19 \times 18 = 342 units; remaining work =360−342=18= 360 - 342 = 18 units.

  • Without C, 2A + 3B produce 6+6=126 + 6 = 12 units/hr, leaving a deficit of 18−12=618 - 12 = 6 units in the 1 hour.

  • Additional members from Team B required =6/2=3= 6 / 2 = 3.

Practice 2 CAT_2025_SLOT3_QA_Q07_SQ02

Teams A, B, and C consist of eight, six, and eight members, respectively, such that every member within a team is equally productive. Working separately, teams A, B, and C can complete a certain job in 30 hours, 20 hours, and 5 hours, respectively. One member from team A, two members from team B, and one member from team C together start the job, and the member from team C leaves after 21 hours. The number of additional member(s) from team B, that would be required to replace the member from team C, to finish the job in the next one hour, is

  1. A

    1

  2. B

    3

  3. C

    2

  4. D

    4

Show answer and solution

Answer: (C)

2

Solution

  • Total member-hours: Team A = 8×30=2408 \times 30 = 240, Team B = 6×20=1206 \times 20 = 120, Team C = 8×5=408 \times 5 = 40.

  • With total work W=240W = 240 units, hourly rates per member are: A = 1, B = 2, C = 6.

  • Initial crew (1A + 2B + 1C) works at 1+4+6=111 + 4 + 6 = 11 units/hr.

  • In 21 hours, work done =21×11=231= 21 \times 11 = 231 units; remaining work =240−231=9= 240 - 231 = 9 units.

  • Without C, 1A + 2B produce 1+4=51 + 4 = 5 units/hr, leaving a deficit of 9−5=49 - 5 = 4 units in 1 hour.

  • Additional members from Team B required =4/2=2= 4 / 2 = 2.

Time & Work questions from other CAT papers

  1. CAT 2024 Slot 1 Quant Q21
    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days…
  2. CAT 2024 Slot 2 Quant Q7
    Amal and Vimal together can complete a task in 150 days, while Vimal and Sunil together can complete the…
  3. CAT 2024 Slot 3 Quant Q20
    Sam can complete a job in 20 days when working alone. Mohit is twice as fast as Sam and thrice as fast as…
  4. CAT 2023 Slot 1 Quant Q16
    The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression.…
  5. CAT 2023 Slot 2 Quant Q8
    Pipes A and C are fill pipes while Pipe B is a drain pipe of a tank. Pipe B empties the full tank in one…

Practise this question with timing, notes and your mistake notebook.

Practise in PrepSoc