Group Work & The Man-Day-Hour Variation Chain (MDHE / W)

Master the unified Man-Day-Hour (MDH) proportionality chain, workforce demographic equivalences (Men, Women, Children), and tactical contractor renegotiations when deadlines are threatened.

1. The Story & Mental Model: Energy as Currency

Think of human labor in terms of pure physics. A single human worker is an engine generating a specific power output:

Work Done=Total Energy Consumed=Power×Time\text{Work Done} = \text{Total Energy Consumed} = \text{Power} \times \text{Time}

If one worker produces EE units of work per hour, and you employ MM workers running for HH hours each day across DD days, the total work output WW delivered is:

W=M×D×H×EW = M \times D \times H \times E

Notice that Work is directly proportional to each factor (M,D,H,EM, D, H, E). Therefore, the ratio of total energy to output produced is invariant:

M×D×H×EW=Constant\frac{M \times D \times H \times E}{W} = \text{Constant}

This single universal law handles every question involving teams of construction workers, factory lines, garrison rations, or excavators.


2. The CAT Question Blueprint: The Three Archetypes

CAT questions on group work test three distinct structural scenarios:

  1. The Pure Proportionality Chain: Changing team size, hours per day, and work dimensions simultaneously (e.g. digging a ditch of length L1L_1 vs L2L_2).

  2. Workforce Demographic Equivalence: Statements like "44 men or 66 women or 1010 children can complete a job in 2020 days". You must find the rate of a mixed composite crew (22 men +3+ 3 women +5+ 5 children).

  3. The Contractor Deadline Crisis: A contractor commits to completing a project in DtargetD_{\text{target}} days with MM men. At an audit on Day DauditD_{\text{audit}}, only a fraction of the work is complete. How many additional workers must be hired to avoid penalties?


3. The Single Tactical Weapon: The Master Proportionality Ratio

A. The Master Chain:

M1⋅D1⋅H1⋅E1W1=M2⋅D2⋅H2⋅E2W2\frac{M_1 \cdot D_1 \cdot H_1 \cdot E_1}{W_1} = \frac{M_2 \cdot D_2 \cdot H_2 \cdot E_2}{W_2}

Where:

  • MM: Number of workers

  • DD: Number of days

  • HH: Working hours per day

  • EE: Relative efficiency per worker

  • WW: Quantity of work (meters of trench, number of shirts, volume of earth moved)

B. The Demographic Equivalence Rule:

When given "aa Men =b= b Women =c= c Children":

  1. Find the LCM of a,b,ca, b, c.

  2. Express individual daily efficiencies as integers:

    EM=LCMa,EW=LCMb,EC=LCMcE_M = \frac{\text{LCM}}{a}, \quad E_W = \frac{\text{LCM}}{b}, \quad E_C = \frac{\text{LCM}}{c}

  3. Replace any composite workforce with equivalent daily efficiency units:

    Ecrew=m⋅EM+w⋅EW+k⋅ECE_{\text{crew}} = m \cdot E_M + w \cdot E_W + k \cdot E_C

C. The Contractor Audit Shortcut:

In contractor problems, NEVER restart calculations from Day 0! Treat the audit day as the starting point:

Mcurrent×DpastWdone=Mnew×DremainingWremaining\frac{M_{\text{current}} \times D_{\text{past}}}{W_{\text{done}}} = \frac{M_{\text{new}} \times D_{\text{remaining}}}{W_{\text{remaining}}}

Solve for MnewM_{\text{new}}, then:

Additional Workers=Mnew−Mcurrent\text{Additional Workers} = M_{\text{new}} - M_{\text{current}}


4. The Classic Exam Trap & Speed Shortcut

The Inverted Work Trap:

The most frequent student mistake is writing M1D1H1W1=M2D2H2W2M_1 D_1 H_1 W_1 = M_2 D_2 H_2 W_2. Work WW is the output, so it goes in the denominator!

The Dimensional Work Trap:

If a trench's dimensions double in length, width, and depth, the work does NOT double—it increases by 2×2×2=82 \times 2 \times 2 = 8 times! Always multiply all physical dimensions to find work WW.

Formulas

Master MDH Variation Chain

M1D1H1E1W1=M2D2H2E2W2\frac{M_1 D_1 H_1 E_1}{W_1} = \frac{M_2 D_2 H_2 E_2}{W_2}

Universal proportionality relation connecting workforce, time, efficiency, and physical output.
Demographic Equivalence Efficiency

aEM=bEW=cEC  ⟹  EM:EW:EC=1a:1b:1ca E_M = b E_W = c E_C \implies E_M : E_W : E_C = \frac{1}{a} : \frac{1}{b} : \frac{1}{c}

Transforms mixed gender/age workforces into unified efficiency units.
Contractor Remaining Work Balance

Mnew=M1×DpastDrem×WremWdoneM_{\text{new}} = M_1 \times \frac{D_{\text{past}}}{D_{\text{rem}}} \times \frac{W_{\text{rem}}}{W_{\text{done}}}

Directly calculates required final team size from the audit date onwards.
Garrison Ration Balance

M1×D1=M2×D2M_1 \times D_1 = M_2 \times D_2

For constant total food supply, worker headcount is inversely proportional to surviving days.

Traps and tips

  • Always put the work quantity (or volume/mass/distance) in the denominator of the MDH fraction.
  • When trench or wall dimensions change, multiply length × width × depth to find the total work volume.
  • For contractor problems, isolate the past work and future work into two separate phases—never calculate from Day 0.
  • In food ration problems, subtract elapsed days from the initial supply before altering the soldier count.

Solved examples

Example 1: Canal Excavation with Changing Dimensions & Hours

A team of 36 excavators working 7 hours a day can dig a drainage canal 140 meters long, 4 meters wide, and 2.5 meters deep in 18 days. How many days will it take for a team of 45 excavators working 8 hours a day to dig another canal that is 280 meters long, 5 meters wide, and 3 meters deep, assuming the soil composition is identical?

Show solution

Step 1: Calculate the work volume for both canals.

  • W1=140×4×2.5=1,400 m3W_1 = 140 \times 4 \times 2.5 = 1,400 \text{ m}^3

  • W2=280×5×3=4,200 m3W_2 = 280 \times 5 \times 3 = 4,200 \text{ m}^3

Notice that W2W1=4,2001,400=3\frac{W_2}{W_1} = \frac{4,200}{1,400} = 3.

Step 2: Apply the MDH formula.

M1⋅D1⋅H1W1=M2⋅D2⋅H2W2\frac{M_1 \cdot D_1 \cdot H_1}{W_1} = \frac{M_2 \cdot D_2 \cdot H_2}{W_2}

36×18×71,400=45×D2×84,200\frac{36 \times 18 \times 7}{1,400} = \frac{45 \times D_2 \times 8}{4,200}

Step 3: Simplify and solve for D2D_2.

36×18×71=45×D2×83\frac{36 \times 18 \times 7}{1} = \frac{45 \times D_2 \times 8}{3}

4536=15×D2×8=120D24536 = 15 \times D_2 \times 8 = 120 D_2

D2=4536120=37.8 daysD_2 = \frac{4536}{120} = 37.8 \text{ days}

Takeaway: Always compute the 3D volume of earth moved before applying MDH to avoid missing geometric scale factors.

Example 2: Demographic Equivalence (Men, Women, Boys)

A manufacturing unit can complete an export garment quota with either 6 men, 9 women, or 12 boys in 30 days. In how many days will the same quota be completed by a composite team consisting of 4 men, 6 women, and 8 boys working together?

Show solution

Step 1: Determine daily efficiency units using LCM.

6M=9W=12B6 M = 9 W = 12 B

LCM(6,9,12)=36\text{LCM}(6, 9, 12) = 36

  • Daily efficiency of 1 Man: EM=366=6 units/dayE_M = \frac{36}{6} = 6 \text{ units/day}

  • Daily efficiency of 1 Woman: EW=369=4 units/dayE_W = \frac{36}{9} = 4 \text{ units/day}

  • Daily efficiency of 1 Boy: EB=3612=3 units/dayE_B = \frac{36}{12} = 3 \text{ units/day}

Step 2: Calculate Total Work.

Using the 6 men benchmark:

Total Work W=(6×6)×30=36×30=1,080 units\text{Total Work } W = (6 \times 6) \times 30 = 36 \times 30 = 1,080 \text{ units}

(Verification using 12 boys: (12×3)×30=1,080(12 \times 3) \times 30 = 1,080 units).

Step 3: Calculate composite team efficiency.

Team Rate=(4×EM)+(6×EW)+(8×EB)\text{Team Rate} = (4 \times E_M) + (6 \times E_W) + (8 \times E_B)

=(4×6)+(6×4)+(8×3)=24+24+24=72 units/day= (4 \times 6) + (6 \times 4) + (8 \times 3) = 24 + 24 + 24 = 72 \text{ units/day}

Step 4: Compute completion days.

Days Required=1,08072=15 days\text{Days Required} = \frac{1,080}{72} = 15 \text{ days}

Takeaway: Equate demographic groups to their LCM to convert mixed workforces into pure integer efficiency units.

Example 3: The Contractor Deadline Crisis

A highway contractor undertakes to pave a 24-kilometer stretch of expressway in 120 days and employs 80 workers. After 75 days, an engineering audit reveals that only 10 kilometers of the expressway have been paved. How many additional workers must the contractor hire immediately to finish the expressway strictly on schedule?

Show solution

Step 1: Segment into Past Work and Remaining Work.

  • Past Phase:

    • Workers: M1=80M_1 = 80

    • Days worked: D1=75D_1 = 75

    • Work done: W1=10 kmW_1 = 10 \text{ km}

  • Future Phase:

    • Days remaining: D2=120−75=45 daysD_2 = 120 - 75 = 45 \text{ days}

    • Work remaining: W2=24−10=14 kmW_2 = 24 - 10 = 14 \text{ km}

    • Workers needed: M2=?M_2 = ?

Step 2: Equate work-rate ratios for the two phases.

M1×D1W1=M2×D2W2\frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2}

80×7510=M2×4514\frac{80 \times 75}{10} = \frac{M_2 \times 45}{14}

Step 3: Solve for M2M_2.

6,00010=600=45M214\frac{6,000}{10} = 600 = \frac{45 M_2}{14}

M2=600×1445=8,40045=5603≈186.67M_2 = \frac{600 \times 14}{45} = \frac{8,400}{45} = \frac{560}{3} \approx 186.67

Since human workers must be integers, the contractor must deploy at least 187187 workers.

Step 4: Additional workers required.

Additional Workers=187−80=107 workers\text{Additional Workers} = 187 - 80 = 107 \text{ workers}

Takeaway: Treat the audit point as a new starting line: compare past output rate directly against future requirements.

Example 4: Fort Garrison Rations with Reinforcements

A military outpost has food provisions sufficient for 600 soldiers for 45 days. After 15 days, a detachment of 300 additional soldiers arrives at the outpost. Assuming daily consumption per soldier remains constant, for how many more days will the remaining provisions last?

Show solution

Step 1: Calculate remaining food supply after 15 days.

Originally, the outpost had provisions for 600 soldiers for 45 days.

After 15 days, the remaining food would sustain the original 600 soldiers for:

Drem=45−15=30 daysD_{\text{rem}} = 45 - 15 = 30 \text{ days}

Remaining Food Supply=600×30=18,000 soldier-days\text{Remaining Food Supply} = 600 \times 30 = 18,000 \text{ soldier-days}

Step 2: Adjust headcount.

300 additional soldiers arrive:

Mnew=600+300=900 soldiersM_{\text{new}} = 600 + 300 = 900 \text{ soldiers}

Step 3: Find days remaining.

D=Remaining Soldier-DaysMnew=18,000900=20 daysD = \frac{\text{Remaining Soldier-Days}}{M_{\text{new}}} = \frac{18,000}{900} = 20 \text{ days}

Takeaway: In ration problems, immediately deduct elapsed days from total supply before modifying the headcount.

Example 5: Mixed Workforce Algebraic Equations

A boutique artisanal workshop employs men and women. 3 men and 4 women can complete a complex weaving order in 16 days. Meanwhile, 4 men and 3 women can complete the same order in 14 days. Find: (1) The ratio of the daily work done by a man to that of a woman, and (2) The number of days taken by 1 man and 1 woman working together to complete the order.

Show solution

Step 1: Set up the total work equality.

Total Work W=(3M+4W)×16=(4M+3W)×14\text{Total Work } W = (3M + 4W) \times 16 = (4M + 3W) \times 14

48M+64W=56M+42W48M + 64W = 56M + 42W

64W−42W=56M−48M64W - 42W = 56M - 48M

22W=8M  ⟹  11W=4M22W = 8M \implies 11W = 4M

MW=114\frac{M}{W} = \frac{11}{4}

Thus, the daily work ratio of 1 man to 1 woman is 11:411 : 4.

Step 2: Assign unit efficiencies.

Let EM=11 units/dayE_M = 11 \text{ units/day} and EW=4 units/dayE_W = 4 \text{ units/day}.

Step 3: Compute Total Work.

W=(3×11+4×4)×16=(33+16)×16=49×16=784 unitsW = (3 \times 11 + 4 \times 4) \times 16 = (33 + 16) \times 16 = 49 \times 16 = 784 \text{ units}

Step 4: Find time for 1 man and 1 woman.

Epair=11+4=15 units/dayE_{\text{pair}} = 11 + 4 = 15 \text{ units/day}

T=78415=52415 days≈52.27 daysT = \frac{784}{15} = 52 \frac{4}{15} \text{ days} \approx 52.27 \text{ days}

Takeaway: Equate two given team descriptions to derive the fundamental individual efficiency ratio M : W .

Example 6: Automated Assembly Line with Machine Downtime

In an automated electronic assembly plant, 12 robotic arms operating 7 hours per day assemble 4,200 microprocessors in 10 days. The plant upgrades to newer models that have 20%20\% higher efficiency, but due to factory power rationing, each arm can only run for 6 hours per day. How many such upgraded robotic arms are required to assemble 7,560 microprocessors in 15 days?

Show solution

Step 1: Define relative efficiencies.

Let the baseline efficiency of the original robotic arm be E1=1.0E_1 = 1.0.

The upgraded arm is 20%20\% more efficient: E2=1.20=65E_2 = 1.20 = \frac{6}{5}.

Step 2: Apply the full MDHE / W formula.

M1⋅D1⋅H1⋅E1W1=M2⋅D2⋅H2⋅E2W2\frac{M_1 \cdot D_1 \cdot H_1 \cdot E_1}{W_1} = \frac{M_2 \cdot D_2 \cdot H_2 \cdot E_2}{W_2}

12×10×7×1.04,200=M2×15×6×1.27,560\frac{12 \times 10 \times 7 \times 1.0}{4,200} = \frac{M_2 \times 15 \times 6 \times 1.2}{7,560}

Step 3: Simplify both sides.

Left Hand Side=8404,200=15=0.2\text{Left Hand Side} = \frac{840}{4,200} = \frac{1}{5} = 0.2

M2×1087,560=0.2\frac{M_2 \times 108}{7,560} = 0.2

M2×108=0.2×7,560=1,512M_2 \times 108 = 0.2 \times 7,560 = 1,512

M2=1,512108=14 robotic armsM_2 = \frac{1,512}{108} = 14 \text{ robotic arms}

Takeaway: When machine efficiency scales alongside time and output, insert the multiplier factor directly into MDHE/W.

Practice questions

Question 1 · CAT Level

A infrastructure contractor undertakes to complete a project in 100100 days using 6060 skilled workers working 88 hours per day. After 5050 days, an audit reveals that only 13\frac{1}{3} of the project is completed. To finish the remaining 23\frac{2}{3} strictly on schedule (in the remaining 5050 days), the daily shift is increased to 1010 hours per day, and the existing skilled workers are augmented by hiring additional semi-skilled workers whose individual efficiency is 75%75\% of a skilled worker. How many semi-skilled workers must be hired?

  1. A

    4040

  2. B

    4444

  3. C

    4848

  4. D

    5454

Show answer and explanation

Answer: (C) 48

Work completed in the first 5050 days: W1=60×50×8×1.0=24,000 unitsW_1 = 60 \times 50 \times 8 \times 1.0 = 24,000\text{ units}.

Since W1=13WtotalW_1 = \frac{1}{3} W_{\text{total}}, remaining work W2=23Wtotal=48,000 unitsW_2 = \frac{2}{3} W_{\text{total}} = 48,000\text{ units}.

In the next 5050 days at 10 h/day10\text{ h/day}, the 6060 skilled workers produce: 60×50×10×1.0=30,000 units60 \times 50 \times 10 \times 1.0 = 30,000\text{ units}.

The deficit to be covered by semi-skilled workers is 48,000−30,000=18,000 units48,000 - 30,000 = 18,000\text{ units}.

Each semi-skilled worker produces 50×10×0.75=375 units50 \times 10 \times 0.75 = 375\text{ units} over the remaining period.

Therefore, number of semi-skilled workers required =18,000375=48= \frac{18,000}{375} = 48.

Question 2 · CAT Level

A production order can be completed by 22 men and 33 women in 1010 days, or by 33 men and 22 women in 88 days. A boy's daily working efficiency is exactly 50%50\% of that of a woman. If 22 men and 11 woman start working on the order and work for 55 days, after which 11 man leaves and 33 boys join the remaining workforce, in how many additional days will the entire order be completed?

  1. A

    88 days

  2. B

    1010 days

  3. C

    1212 days

  4. D

    1414 days

Show answer and explanation

Answer: (B) 10 days

Equating total work: (2M+3W)×10=(3M+2W)×8  ⟹  20M+30W=24M+16W  ⟹  4M=14W  ⟹  MW=72(2M + 3W) \times 10 = (3M + 2W) \times 8 \implies 20M + 30W = 24M + 16W \implies 4M = 14W \implies \frac{M}{W} = \frac{7}{2}.

Let EM=7 units/dayE_M = 7\text{ units/day}, EW=2 units/dayE_W = 2\text{ units/day}, and EB=0.5×2=1 unit/dayE_B = 0.5 \times 2 = 1\text{ unit/day}.

Total work W=(2×7+3×2)×10=20×10=200 unitsW = (2 \times 7 + 3 \times 2) \times 10 = 20 \times 10 = 200\text{ units}.

Phase 1 (55 days): Rate =2(7)+1(2)=16 units/day  ⟹  Work done=5×16=80 units= 2(7) + 1(2) = 16\text{ units/day} \implies \text{Work done} = 5 \times 16 = 80\text{ units}; remaining =120 units= 120\text{ units}.

Phase 2: Workforce is 1M+1W+3B  ⟹  Rate=1(7)+1(2)+3(1)=12 units/day1M + 1W + 3B \implies \text{Rate} = 1(7) + 1(2) + 3(1) = 12\text{ units/day}.

Additional days required =12012=10 days= \frac{120}{12} = 10\text{ days}.

Question 3 · CAT Level

A military outpost has provisions sufficient for 1,2001,200 soldiers for 7070 days, with each soldier consuming 900 grams900\text{ grams} daily. After 2020 days, 300300 additional soldiers arrive at the fort, and the daily ration per soldier is simultaneously reduced to 750 grams750\text{ grams}. After 2020 days under this new regime, 500500 soldiers are evacuated to another post. If rations remain at 750 grams750\text{ grams} per soldier, for how many further days from the evacuation date will the remaining food supply last?

  1. A

    3636 days

  2. B

    4040 days

  3. C

    4242 days

  4. D

    4545 days

Show answer and explanation

Answer: (C) 42 days

At Day 20, remaining food for 1,2001,200 soldiers is for 5050 days at 900 g/day900\text{ g/day}: 1,200×50×900=54,000,000 g1,200 \times 50 \times 900 = 54,000,000\text{ g}.

Under 1,5001,500 soldiers at 750 g/day750\text{ g/day}, daily burn is 1,125,000 g/day1,125,000\text{ g/day}, so food would last 54,000,0001,125,000=48 days\frac{54,000,000}{1,125,000} = 48\text{ days}.

After 2020 days of this regime, food remaining for 1,5001,500 soldiers equals 48−20=28 days48 - 20 = 28\text{ days} of consumption.

When 500500 soldiers are evacuated, the surviving garrison becomes 1,500−500=1,0001,500 - 500 = 1,000 soldiers.

By inverse proportionality: D=28×1,5001,000=28×1.5=42 daysD = 28 \times \frac{1,500}{1,000} = 28 \times 1.5 = 42\text{ days}.

Question 4 · CAT Level

A fleet of 2424 automated paving machines operating 88 hours per day can lay a road of length 18 km18\text{ km}, width 12 m12\text{ m}, and thickness 15 cm15\text{ cm} in 2525 days. A second contract requires laying a road of length 27 km27\text{ km}, width 16 m16\text{ m}, and thickness 20 cm20\text{ cm} in 3232 days. If upgraded paving machines with 25%25\% higher individual efficiency are deployed and operated for 1010 hours per day, how many upgraded machines are required?

  1. A

    2828

  2. B

    3030

  3. C

    3232

  4. D

    3636

Show answer and explanation

Answer: (C) 32

Calculate volume ratio: W2W1=27×16×2018×12×15=32×43×43=83\frac{W_2}{W_1} = \frac{27 \times 16 \times 20}{18 \times 12 \times 15} = \frac{3}{2} \times \frac{4}{3} \times \frac{4}{3} = \frac{8}{3}.

Given efficiency ratio E2E1=1.25=54\frac{E_2}{E_1} = 1.25 = \frac{5}{4}, apply the universal variation chain: M1D1H1E1W1=M2D2H2E2W2\frac{M_1 D_1 H_1 E_1}{W_1} = \frac{M_2 D_2 H_2 E_2}{W_2}.

Rearranging: M2=M1×(D1D2)×(H1H2)×(E1E2)×(W2W1)M_2 = M_1 \times \left(\frac{D_1}{D_2}\right) \times \left(\frac{H_1}{H_2}\right) \times \left(\frac{E_1}{E_2}\right) \times \left(\frac{W_2}{W_1}\right).

Substituting: M2=24×(2532)×(810)×(45)×(83)M_2 = 24 \times \left(\frac{25}{32}\right) \times \left(\frac{8}{10}\right) \times \left(\frac{4}{5}\right) \times \left(\frac{8}{3}\right).

Simplifying: M2=24×(2532×1625)×83=24×12×83=32 machinesM_2 = 24 \times \left(\frac{25}{32} \times \frac{16}{25}\right) \times \frac{8}{3} = 24 \times \frac{1}{2} \times \frac{8}{3} = 32\text{ machines}.

Question 5 · CAT Level

A software firm estimates that a group of developers can build an enterprise platform in 3030 days working standard 88-hour shifts. However, at the end of every 1010 days, exactly 88 developers leave the project. To compensate for the shrinking team, starting from Day 2121, the remaining developers increase their daily shift length by 20%20\% (from 88 hours to 9.69.6 hours). If the entire platform is completed in exactly 4040 days, how many developers originally started the project on Day 11?

  1. A

    3232

  2. B

    3636

  3. C

    4040

  4. D

    4848

Show answer and explanation

Answer: (C) 40

Let NN be the initial developers. Total work W=30N developer-daysW = 30N\text{ developer-days} at the standard 8 h/day8\text{ h/day} rate.

Days 1–10 (1.0×1.0\times rate): W1=10N unitsW_1 = 10N\text{ units}.

Days 11–20 (1.0×1.0\times rate): N−8N - 8 developers work   ⟹  W2=10(N−8)=10N−80 units\implies W_2 = 10(N - 8) = 10N - 80\text{ units}.

Days 21–30 (1.2×1.2\times rate): N−16N - 16 developers work   ⟹  W3=10×1.2(N−16)=12N−192 units\implies W_3 = 10 \times 1.2(N - 16) = 12N - 192\text{ units}.

Days 31–40 (1.2×1.2\times rate): N−24N - 24 developers work   ⟹  W4=10×1.2(N−24)=12N−288 units\implies W_4 = 10 \times 1.2(N - 24) = 12N - 288\text{ units}.

Summing work done: 10N+(10N−80)+(12N−192)+(12N−288)=44N−560=30N  ⟹  14N=560  ⟹  N=4010N + (10N - 80) + (12N - 192) + (12N - 288) = 44N - 560 = 30N \implies 14N = 560 \implies N = 40.