CAT 2021 Slot 3 DILR Q15
- Data Interpretation and Logical Reasoning
- Data Interpretation › Other Charts
- Easy
- Multiple choice
- CAT_2021_SLOT3_DILR_Q15
Data set · questions 13–16
The figure above shows the schedule of four employees – Abani, Bahni, Danni and Tinni –whom Dhoni supervised in 2020. Altogether there were five projects which started and concluded in 2020 in which they were involved. For each of these projects and for each employee, the starting day was at the beginning of a month and the concluding day was the end of a month, and these are indicated by the left and right end points of the corresponding horizontal bars. The number within each bar indicates the percentage of assigned work completed by the employee for that project, as assessed by Dhoni.
For each employee, his/her total project-month (in 2020) is the sum of the number of months(s)he worked across the five project, while his/her annual completion index is the weight age average of the completion percentage assigned from the different projects, with the weights being the corresponding number of months she worked in these projects. For each project, the total employee-month is the sum of the number of months four employees worked in this project, while its completion index is the weight age average of the completion percentage assigned for the employees who worked in this project, with the weights being the corresponding number of months they worked in this project.
Question 15
The project duration, measured in terms of the number of months, is the time duringwhich at least one employee worked in the project. Which of the following pairs of theprojects had the same duration?
Show answer and solution
Answer: (C)
Project 3, Project 4
Solution
Concept: Interval Union, Span Calculation & Project Duration Matching
Master State Table
| Project | Active Span | Duration | Abani | Bahni | Danni | Tinni | Total Emp-Mo |
|---|---|---|---|---|---|---|---|
| Project 1 | Jan 1 – Apr 1 | 3 Months | Feb–Apr (2 mo, 100%) | Feb–Apr (2 mo, 100%) | — | Jan–Mar (2 mo, 80%) | 6 Months |
| Project 2 | Feb 1 – May 1 | 3 Months | — | — | Feb–May (3 mo, 90%) | Mar–May (2 mo, 100%) | 5 Months |
| Project 3 | Apr 1 – Sep 1 | 5 Months | May–Jul (2 mo, 100%) | Apr–Aug (4 mo, 75%) | Jun–Sep (3 mo, 100%) | — | 9 Months |
| Project 4 | Jul 1 – Dec 1 | 5 Months | Jul–Dec (5 mo, 80%) | — | Sep–Nov (2 mo, 100%) | Jul–Oct (3 mo, 100%) | 10 Months |
| Project 5 | Sep 1 – Jan 1 | 4 Months | — | Oct–Jan (3 mo, 90%) | Dec–Jan (1 mo, 100%) | Sep–Nov (2 mo, 100%) | 6 Months |
| Total Project-Months | — | — | 9 Months | 9 Months | 9 Months | 9 Months | 36 Months |
| Annual Completion Index | — | — | 88.89% | 85.56% | 96.67% | 95.56% | — |
Question Deduction
• Understanding Project Duration Definition:
• Project duration is defined as the elapsed time in months during which at least one employee worked on the project.
• Duration equals the continuous span from the earliest start month of any contributing employee to the latest concluding month among them.
• Calculating Duration for All Five Projects:
• Project 1: Starts Jan 1 (Tinni), ends Apr 1 (Abani, Bahni) active Jan–Mar ( months).
• Project 2: Starts Feb 1 (Danni), ends May 1 (Danni, Tinni) active Feb–Apr ( months).
• Project 3: Starts Apr 1 (Bahni), ends Sep 1 (Danni) active Apr–Aug ( months).
• Project 4: Starts Jul 1 (Abani, Tinni), ends Dec 1 (Abani) active Jul–Nov ( months).
• Project 5: Starts Sep 1 (Tinni), ends Jan 1 (Bahni, Danni) active Sep–Dec ( months).
• Comparing Project Durations Across Options:
• Summary: mo, mo, mo, mo, mo.
• Pairs with matching duration: and .
• Evaluating options:
• Option 1: Project 4 (5 mo), Project 5 (4 mo) $\implies$ Different.
• Option 2: Project 3 (5 mo), Project 5 (4 mo) $\implies$ Different.
• Option 3: Project 3 (5 mo), Project 4 (5 mo) $\implies$ Identical ($5 = 5$).
• Option 4: Project 1 (3 mo), Project 5 (4 mo) $\implies$ Different.
• Option Matching / Numerical Answer:
• Matches Option 3 (Project 3, Project 4).
Topper Take
• Boundary Scan: Read left-most start and right-most end per project row. Project 3 runs Apr–Sep (5 mo) and Project 4 runs Jul–Dec (5 mo), directly selecting Option 3.
Other questions in this set
- Q13. Which of the following statements is/are true? I: The total project-month was the same for the four employees. II: The…
- Q14. Which employees did not work in multiple projects for any of the months in 2020?
- Q16. The list of employees in decreasing order of annual completion index is:
Other Charts questions from other CAT papers
- CAT 2025 Slot 1 DILR Q1
- CAT 2025 Slot 1 DILR Q2
- CAT 2025 Slot 1 DILR Q3
- CAT 2025 Slot 1 DILR Q4
- CAT 2025 Slot 3 DILR Q6
Practise this question with timing, notes and your mistake notebook.
Practise in PrepSoc