CAT 2022 Slot 2 Quant Q4
- Quantitative Aptitude
- Arithmetic › Time & Work
- Medium
- Type in the answer (TITA)
- CAT_2022_SLOT2_QA_Q04
Question 4
Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio . They accept a job which they can finish in days if they all work together for hours per day. However, Anu and Tanu work together for the first days, working hours minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
6
Solution
-
Time ratio = Efficiency ratio = .
-
Total work = (Total Efficiency) Time = units.
-
Anu + Tanu work for = hours.
-
Work done by Anu + Tanu = units.
-
Remaining work = units.
-
Manu's time for remaining work = hours.
Detailed explanation
Concept: Time and Work.
-
Ratio of times taken by Anu, Tanu, Manu = .
-
Ratio of their efficiencies (work done per hour) = .
-
Multiplying by LCM(5,8,10) = 40, we get the efficiency ratio = .
-
Let Anu's, Tanu's, and Manu's efficiency be , and per hour.
-
Combined efficiency = per hour.
-
Total time they worked together = hours.
-
Total Work () = Combined Efficiency Total Time = .
-
Now, Anu and Tanu work together for 6 days, 6 hours 40 minutes per day.
-
Daily hours = hours.
-
Total hours worked by Anu and Tanu = hours.
-
Anu + Tanu efficiency = .
-
Work completed by them = .
-
Remaining work = .
-
Manu's efficiency = per hour.
-
Time required for Manu to complete remaining work = hours.
Practise similar questions
Practice 1 CAT_2022_SLOT2_QA_Q04_SQ01
Working alone, the times taken by Aakash, Bharat and Chetan to complete any job are in the ratio . They accept a job which they can finish in days if they all work together for hours per day. However, Aakash and Bharat work together for the first days, working hours minutes per day. Then, the number of hours that Chetan will take to complete the remaining job working alone is
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
6
Solution
-
Time ratio = Efficiency ratio = .
-
Total work = units.
-
Aakash and Bharat work for hours.
-
Work done by Aakash and Bharat = units.
-
Remaining work = units.
-
Chetan's time = hours.
Practice 2 CAT_2022_SLOT2_QA_Q04_SQ02
Working alone, the times taken by Divya, Esha and Farah to complete any job are in the ratio . They accept a job which they can finish in days if they all work together for hours per day. However, Divya and Esha work together for the first days, working hours minutes per day. Then, the number of hours that Farah will take to complete the remaining job working alone is
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
12
Solution
-
Time ratio = Efficiency ratio = .
-
Total work = units.
-
Divya and Esha work for hours.
-
Work done by Divya and Esha = units.
-
Remaining work = units.
-
Farah's time = hours.
Time & Work questions from other CAT papers
- CAT 2025 Slot 1 Quant Q16
- CAT 2025 Slot 2 Quant Q10
- CAT 2025 Slot 3 Quant Q7
- CAT 2025 Slot 3 Quant Q13
- CAT 2024 Slot 1 Quant Q21
Practise this question with timing, notes and your mistake notebook.
Practise in PrepSoc