CAT 2021 Slot 2 Quant Q22

  • Quantitative Aptitude
  • Arithmetic › Time & Work
  • Medium
  • Multiple choice
  • CAT_2021_SLOT2_QA_Q22

Question 22

Anil can paint a house in 6060 days while Bimal can paint it in 8484 days. Anil starts painting and after 1010 days, Bimal and Charu join him. Together, they complete the painting in 1414 more days. If they are paid a total of Rs. 2100021000 for the job, then the share of Charu, in INR, proportionate to the work done by him, is

  1. A

    91009100

    Answer A in PrepSoc practice
  2. B

    91509150

    Answer B in PrepSoc practice
  3. C

    90009000

    Answer C in PrepSoc practice
  4. D

    92009200

    Answer D in PrepSoc practice

Answer this questionOr tap an option. Opens in practice mode, free, no sign-in.

Show answer and solution

Answer: (A)

91009100

Solution

  • Anil works 2424 days   ⟹  Fraction done=2460=25\implies \text{Fraction done} = \frac{24}{60} = \frac{2}{5}.

  • Bimal works 1414 days   ⟹  Fraction done=1484=16\implies \text{Fraction done} = \frac{14}{84} = \frac{1}{6}.

  • Combined fraction of Anil and Bimal =25+16=1730= \frac{2}{5} + \frac{1}{6} = \frac{17}{30}.

  • Charu's fraction =1−1730=1330= 1 - \frac{17}{30} = \frac{13}{30}.

  • Charu's share =1330×21000=13×700=9100= \frac{13}{30} \times 21000 = 13 \times 700 = 9100.

Detailed explanation

Concept: Time and Work, Proportionate Wages.

  1. Let the total work be the LCM of 6060 and 8484.

    • LCM(60,84)=420\text{LCM}(60, 84) = 420 units.
  2. Calculate the daily work efficiency of Anil and Bimal:

    • Anil's efficiency =42060=7= \frac{420}{60} = 7 units/day

    • Bimal's efficiency =42084=5= \frac{420}{84} = 5 units/day

  3. Determine the duration each person worked:

    • Anil worked for 10+14=2410 + 14 = 24 days.

    • Bimal worked for 1414 days.

    • Charu worked for 1414 days.

  4. Calculate the work completed by Anil and Bimal:

    • Work done by Anil =24×7=168= 24 \times 7 = 168 units

    • Work done by Bimal =14×5=70= 14 \times 5 = 70 units

    • Combined work of Anil and Bimal =168+70=238= 168 + 70 = 238 units

  5. Calculate the work done by Charu:

    • Work done by Charu =420−238=182= 420 - 238 = 182 units
  6. The payment is proportional to the fraction of total work done:

    • Charu's share =(182420)×21000=182×50=Rs. 9100= \left(\frac{182}{420}\right) \times 21000 = 182 \times 50 = \text{Rs. } 9100.

Practise similar questions

Practice 1 CAT_2021_SLOT2_QA_Q22_SQ01

David can complete a park landscaping project in 4848 days while Ethan can complete it in 7272 days. David starts the work and after 66 days, Ethan and Farhan join him. Together, they complete the landscaping in 1414 more days. If they are paid a total of Rs. 3600036000 for the job, then the share of Farhan, in INR, proportionate to the work done by him, is

  1. A

    1400014000

  2. B

    1440014400

  3. C

    1380013800

  4. D

    1500015000

Show answer and solution

Answer: (A)

1400014000

Solution

  • David works 6+14=206 + 14 = 20 days   ⟹  Fraction=2048=512\implies \text{Fraction} = \frac{20}{48} = \frac{5}{12}.

  • Ethan works 1414 days   ⟹  Fraction=1472=736\implies \text{Fraction} = \frac{14}{72} = \frac{7}{36}.

  • Combined fraction of David and Ethan =512+736=1118= \frac{5}{12} + \frac{7}{36} = \frac{11}{18}.

  • Farhan's fraction =1−1118=718= 1 - \frac{11}{18} = \frac{7}{18}.

  • Farhan's share =718×36000=14000= \frac{7}{18} \times 36000 = 14000, matching Option 1.

Practice 2 CAT_2021_SLOT2_QA_Q22_SQ02

Rajesh can lay an optical fiber cable network in 5454 days while Suresh can lay it in 9090 days. Rajesh starts the work alone and after 99 days, Suresh and Tarun join him. Together, they complete the cable laying in 1818 more days. If they are paid a total of Rs. 4500045000 for the job, then the share of Tarun, in INR, proportionate to the work done by him, is

  1. A

    1320013200

  2. B

    1350013500

  3. C

    1400014000

  4. D

    1380013800

Show answer and solution

Answer: (B)

1350013500

Solution

  • Rajesh works 9+18=279 + 18 = 27 days   ⟹  Fraction=2754=12\implies \text{Fraction} = \frac{27}{54} = \frac{1}{2}.

  • Suresh works 1818 days   ⟹  Fraction=1890=15\implies \text{Fraction} = \frac{18}{90} = \frac{1}{5}.

  • Combined fraction of Rajesh and Suresh =12+15=710= \frac{1}{2} + \frac{1}{5} = \frac{7}{10}.

  • Tarun's fraction =1−710=310= 1 - \frac{7}{10} = \frac{3}{10}.

  • Tarun's share =310×45000=13500= \frac{3}{10} \times 45000 = 13500, matching Option 2.

Time & Work questions from other CAT papers

  1. CAT 2025 Slot 1 Quant Q16
    Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They…
  2. CAT 2025 Slot 2 Quant Q10
    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start…
  3. CAT 2025 Slot 3 Quant Q7
    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a…
  4. CAT 2025 Slot 3 Quant Q13
    The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be…
  5. CAT 2024 Slot 1 Quant Q21
    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days…

Practise this question with timing, notes and your mistake notebook.

Practise in PrepSoc