Question 4

Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is

  1. A

    66

    Answer A in PrepSoc practice
  2. B

    77

    Answer B in PrepSoc practice
  3. C

    88

    Answer C in PrepSoc practice
  4. D

    55

    Answer D in PrepSoc practice

Answer this questionOr tap an option. Opens in practice mode, free, no sign-in.

Show answer and solution

Answer: (B)

77

Solution

  • Total Work = LCM(15, 12, 20) = 60 units.

  • Per day rates: Anu=4, Vinu=5, Manu=3.

  • Cycle (Day 1): Anu + Vinu = 9 units.

  • Cycle (Day 2): Manu + Vinu = 8 units.

  • 2-day cycle = 17 units.

  • 3 cycles (6 days) = 17×3=5117 \times 3 = 51 units.

  • Remaining work = 9 units.

  • Day 7 is Anu + Vinu, who do exactly 9 units. Thus, 7 days total.

Detailed explanation

Concept: Time and Work (LCM Method)

  1. Let the total work be the LCM of the individual times taken by Anu, Vinu, and Manu.

    Total Work=LCM(15,12,20)=60 units\text{Total Work} = \text{LCM}(15, 12, 20) = 60 \text{ units}

  2. Calculate their individual efficiencies (work done per day):

    • Anu's efficiency: 60/15=4 units/day60 / 15 = 4 \text{ units/day}

    • Vinu's efficiency: 60/12=5 units/day60 / 12 = 5 \text{ units/day}

    • Manu's efficiency: 60/20=3 units/day60 / 20 = 3 \text{ units/day}

  3. Determine the daily work schedule based on the given conditions:

    • Day 1: Anu and Vinu work   ⟹  4+5=9 units\implies 4 + 5 = 9 \text{ units}

    • Day 2: Vinu and Manu work   ⟹  5+3=8 units\implies 5 + 3 = 8 \text{ units}

    • This 2-day cycle repeats.

  4. Work done in one 2-day cycle = 9+8=17 units9 + 8 = 17 \text{ units}.

  5. After 3 full cycles (6 days6 \text{ days}), the work completed is:

    3×17=51 units3 \times 17 = 51 \text{ units}

  6. Remaining work = 60−51=9 units60 - 51 = 9 \text{ units}.

  7. On the 7th day, it's the start of a new cycle, so Anu and Vinu work together. They complete exactly 9 units9 \text{ units} in one day.

  8. The total time taken to complete the work is exactly 6+1=7 days6 + 1 = 7 \text{ days}.

Practise similar questions

Practice 1 CAT_2021_SLOT1_QA_Q04_SQ01

Kabir, Riya, and Dev can complete a graphic design project alone in 10 days10\text{ days}, 12 days12\text{ days}, and 15 days15\text{ days}, respectively. Riya works every day. Kabir works only on alternate days starting from the first day, while Dev works only on alternate days starting from the second day. Then, the number of days needed to complete the project is

  1. A

    55

  2. B

    66

  3. C

    77

  4. D

    88

Show answer and solution

Answer: (B)

66

Solution

  • Total Work = LCM(10, 12, 15) = 60 units.

  • Daily efficiencies: Kabir = 6, Riya = 5, Dev = 4 units/day.

  • Day 1 (Kabir + Riya) = 6 + 5 = 11 units.

  • Day 2 (Dev + Riya) = 4 + 5 = 9 units.

  • 2-day cycle output = 11 + 9 = 20 units.

  • Number of cycles to finish = 60 / 20 = 3 cycles.

  • Total days = 3 * 2 = 6 days.

  • Matches Option 2.

Practice 2 CAT_2021_SLOT1_QA_Q04_SQ02

Rohan, Priya, and Amit can renovate an art studio alone in 12 days12\text{ days}, 16 days16\text{ days}, and 24 days24\text{ days}, respectively. Priya works every day. Rohan works only on alternate days starting from the first day, while Amit works only on alternate days starting from the second day. Then, the number of days needed to complete the renovation is

  1. A

    77

  2. B

    88

  3. C

    99

  4. D

    1010

Show answer and solution

Answer: (B)

88

Solution

  • Total Work = LCM(12, 16, 24) = 48 units.

  • Efficiencies: Rohan = 4, Priya = 3, Amit = 2 units/day.

  • Day 1 (Rohan + Priya) = 4 + 3 = 7 units.

  • Day 2 (Amit + Priya) = 2 + 3 = 5 units.

  • 2-day cycle = 7 + 5 = 12 units.

  • Cycles needed = 48 / 12 = 4 cycles.

  • Total days = 4 * 2 = 8 days.

  • Matches Option 2.

Time & Work questions from other CAT papers

  1. CAT 2025 Slot 1 Quant Q16
    Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They…
  2. CAT 2025 Slot 2 Quant Q10
    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start…
  3. CAT 2025 Slot 3 Quant Q7
    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a…
  4. CAT 2025 Slot 3 Quant Q13
    The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be…
  5. CAT 2024 Slot 1 Quant Q21
    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days…

Practise this question with timing, notes and your mistake notebook.

Practise in PrepSoc