Question 24
A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?
Type-in-the-answer (TITA) question: no options are given; enter the value.
Answer this question Opens in practice mode, free, no sign-in.
Show answer and solution
Answer:
40
Solution
-
Work ratio: W1W2=1.5 km4.5 km=3 times the work.
-
At the current pace, 140 men need 3×60=180 days to finish 4.5 km.
-
But we only have 140 days left!
-
Since Men×Days=Constant:
M2×140=140×180⟹M2=180
-
Extra men required =180−140=40.
Detailed explanation
Concept: Time and Work (Unitary Method / Work-Rate Equivalence).
-
Given Data:
-
Total road length = 6 km, Total scheduled time = 200 days.
-
Initial workforce (M1) = 140 persons.
-
Work completed in initial period (W1) = 1.5 km in T1=60 days.
-
Remaining Requirements:
-
Remaining work (W2) = 6−1.5=4.5 km.
-
Remaining time available (T2) = 200−60=140 days.
-
Let total workforce required for the remaining period be M2.
-
Applying the Work-Equivalence Formula:
W1M1×T1=W2M2×T2
-
Substituting the values:
1.5140×60=4.5M2×140
-
Solving for M2:
1.560=4.5M2⟹M2=60×3=180 persons
-
Additional Workforce Needed:
ΔM=M2−M1=180−140=40
Practise similar questions
Practice 1 CAT_2020_SLOT3_QA_Q24_SQ01
A contractor agreed to dig a 10 km irrigation canal in 150 days and deployed 90 workers for the project. After 50 days, he observed that only 2.5 km of the canal had been completed. How many additional workers must he employ to finish the project strictly on schedule?
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
45
Solution
-
Work remaining ratio: W2/W1=7.5/2.5=3 times the work.
-
At the initial rate, 90 workers would need 3×50=150 days to complete 7.5 km.
-
Available time is only 100 days.
-
Since Workers×Days=Constant:
-
M2×100=90×150⟹M2=135
-
Additional workers needed =135−90=45.
Practice 2 CAT_2020_SLOT3_QA_Q24_SQ02
A civil engineering firm contracted to lay a 12 km railway track in 180 days with a crew of 120 laborers. After 60 days, only 3 km of the track had been laid. How many additional laborers must be hired to complete the track on the scheduled deadline?
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
60
Solution
-
Work remaining ratio: W2/W1=9/3=3 times the work.
-
At the current pace, 120 men need 3×60=180 days to complete the remaining 9 km.
-
Time left is only 120 days.
-
Equating total person-days:
-
M2×120=120×180⟹M2=180
-
Additional laborers required =180−120=60.
Time & Work questions from other CAT papers
- CAT 2025 Slot 1 Quant Q16
Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They…
- CAT 2025 Slot 2 Quant Q10
Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start…
- CAT 2025 Slot 3 Quant Q7
Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a…
- CAT 2025 Slot 3 Quant Q13
The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be…
- CAT 2024 Slot 1 Quant Q21
Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days…