CAT 2020 Slot 3 Quant Q24

  • Quantitative Aptitude
  • Arithmetic › Time & Work
  • Medium
  • Type in the answer (TITA)
  • CAT_2020_SLOT3_QA_Q24

Question 24

A contractor agreed to construct a 66 km road in 200200 days. He employed 140140 persons for the work. After 6060 days, he realized that only 1.51.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?

Type-in-the-answer (TITA) question: no options are given; enter the value.

Answer this question Opens in practice mode, free, no sign-in.

Show answer and solution

Answer:

40

Solution

  • Work ratio: W2W1=4.5 km1.5 km=3\frac{W_2}{W_1} = \frac{4.5\text{ km}}{1.5\text{ km}} = 3 times the work.

  • At the current pace, 140140 men need 3×60=180 days3 \times 60 = 180\text{ days} to finish 4.5 km4.5\text{ km}.

  • But we only have 140 days140\text{ days} left!

  • Since Men×Days=Constant\text{Men} \times \text{Days} = \text{Constant}:

    M2×140=140×180  ⟹  M2=180M_2 \times 140 = 140 \times 180 \implies M_2 = 180

  • Extra men required =180−140=40= 180 - 140 = 40.

Detailed explanation

Concept: Time and Work (Unitary Method / Work-Rate Equivalence).

  1. Given Data:

    • Total road length = 6 km6\text{ km}, Total scheduled time = 200 days200\text{ days}.

    • Initial workforce (M1M_1) = 140 persons140\text{ persons}.

    • Work completed in initial period (W1W_1) = 1.5 km1.5\text{ km} in T1=60 daysT_1 = 60\text{ days}.

  2. Remaining Requirements:

    • Remaining work (W2W_2) = 6−1.5=4.5 km6 - 1.5 = 4.5\text{ km}.

    • Remaining time available (T2T_2) = 200−60=140 days200 - 60 = 140\text{ days}.

    • Let total workforce required for the remaining period be M2M_2.

  3. Applying the Work-Equivalence Formula:

    M1×T1W1=M2×T2W2\frac{M_1 \times T_1}{W_1} = \frac{M_2 \times T_2}{W_2}

  4. Substituting the values:

    140×601.5=M2×1404.5\frac{140 \times 60}{1.5} = \frac{M_2 \times 140}{4.5}

  5. Solving for M2M_2:

    601.5=M24.5  ⟹  M2=60×3=180 persons\frac{60}{1.5} = \frac{M_2}{4.5} \implies M_2 = 60 \times 3 = 180\text{ persons}

  6. Additional Workforce Needed:

    ΔM=M2−M1=180−140=40\Delta M = M_2 - M_1 = 180 - 140 = 40

Practise similar questions

Practice 1 CAT_2020_SLOT3_QA_Q24_SQ01

A contractor agreed to dig a 10 km10\text{ km} irrigation canal in 150 days150\text{ days} and deployed 90 workers90\text{ workers} for the project. After 50 days50\text{ days}, he observed that only 2.5 km2.5\text{ km} of the canal had been completed. How many additional workers must he employ to finish the project strictly on schedule?

Type-in-the-answer (TITA) question: no options are given; enter the value.

Show answer and solution

Answer:

45

Solution

  • Work remaining ratio: W2/W1=7.5/2.5=3W_2 / W_1 = 7.5 / 2.5 = 3 times the work.

  • At the initial rate, 9090 workers would need 3×50=150 days3 \times 50 = 150\text{ days} to complete 7.5 km7.5\text{ km}.

  • Available time is only 100 days100\text{ days}.

  • Since Workers×Days=Constant\text{Workers} \times \text{Days} = \text{Constant}:

  • M2×100=90×150  ⟹  M2=135M_2 \times 100 = 90 \times 150 \implies M_2 = 135

  • Additional workers needed =135−90=45= 135 - 90 = 45.

Practice 2 CAT_2020_SLOT3_QA_Q24_SQ02

A civil engineering firm contracted to lay a 12 km12\text{ km} railway track in 180 days180\text{ days} with a crew of 120 laborers120\text{ laborers}. After 60 days60\text{ days}, only 3 km3\text{ km} of the track had been laid. How many additional laborers must be hired to complete the track on the scheduled deadline?

Type-in-the-answer (TITA) question: no options are given; enter the value.

Show answer and solution

Answer:

60

Solution

  • Work remaining ratio: W2/W1=9/3=3W_2 / W_1 = 9 / 3 = 3 times the work.

  • At the current pace, 120120 men need 3×60=180 days3 \times 60 = 180\text{ days} to complete the remaining 9 km9\text{ km}.

  • Time left is only 120 days120\text{ days}.

  • Equating total person-days:

  • M2×120=120×180  ⟹  M2=180M_2 \times 120 = 120 \times 180 \implies M_2 = 180

  • Additional laborers required =180−120=60= 180 - 120 = 60.

Time & Work questions from other CAT papers

  1. CAT 2025 Slot 1 Quant Q16
    Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They…
  2. CAT 2025 Slot 2 Quant Q10
    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start…
  3. CAT 2025 Slot 3 Quant Q7
    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a…
  4. CAT 2025 Slot 3 Quant Q13
    The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be…
  5. CAT 2024 Slot 1 Quant Q21
    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days…

Practise this question with timing, notes and your mistake notebook.

Practise in PrepSoc