CAT 2020 Slot 2 Quant Q23
- Quantitative Aptitude
- Arithmetic › Time & Work
- Medium
- Type in the answer (TITA)
- CAT_2020_SLOT2_QA_Q23
Question 23
John takes twice as much time as Jack to finish a job. Jack and Jim together take one-thirds of the time to finish the job than John takes working alone. Moreover, in order to finish the job, John takes three days more than that taken by three of them working together. In how many days will Jim finish the job working alone?
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
4
Solution
-
Let Jack take days John takes days.
-
Jack + Jim take days Combined rate .
-
Jim's rate Jim takes days (same rate as John).
-
All three combined rate Time taken .
-
Difference: .
-
Jim alone takes days.
Detailed explanation
Concept: Time and Work / Work Rates.
-
Let the time taken by Jack to finish the job alone be days.
-
John takes twice as much time as Jack:
-
days
-
John's work rate of the job per day
-
Jack's work rate of the job per day
-
-
Jack and Jim together take one-third the time John takes alone:
-
days
-
Combined rate of Jack and Jim
-
-
Determine Jim's work rate:
-
-
-
Jim alone takes days to complete the job.
-
-
Work rate of all three together:
-
-
Time taken by all three together days.
-
-
According to the problem, John takes days more than all three together:
-
Time taken by Jim alone:
.
Practise similar questions
Practice 1 CAT_2020_SLOT2_QA_Q23_SQ01
Amit takes three times as much time as Bharat to finish a job. Bharat and Chetan together take one-fourth of the time to finish the job that Amit takes working alone. Moreover, in order to finish the job, Amit takes days more than the time taken by all three of them working together. In how many days will Chetan finish the job working alone?
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
15
Solution
-
Let Bharat take days Amit takes days.
-
Bharat and Chetan take days Combined rate .
-
Chetan's rate Chetan takes days.
-
All three combined rate Time together days.
-
Difference: .
-
Chetan alone takes days.
Practice 2 CAT_2020_SLOT2_QA_Q23_SQ02
Dan takes twice as much time as Leo to finish a project. Leo and Max together take one-fifth of the time Dan takes alone. Moreover, in order to finish the project, Dan takes days more than the time taken by all three of them working together. In how many days will Max finish the project working alone?
Type-in-the-answer (TITA) question: no options are given; enter the value.
Show answer and solution
Answer:
4
Solution
-
Let Leo take days Dan takes days.
-
Leo and Max take days Combined rate .
-
Max's rate Max takes days.
-
All three combined rate Time together days.
-
Difference: .
-
Max alone takes days.
Time & Work questions from other CAT papers
- CAT 2025 Slot 1 Quant Q16
- CAT 2025 Slot 2 Quant Q10