Question 13

Amal can complete a job in 1010 days and Bimal can complete it in 88 days. Amal, Bimal and Kamal together complete the job in 44 days and are paid a total amount of Rs 10001000 as remuneration. If this amount is shared by them in proportion to their work, then Kamal's share, in rupees, is

  1. A

    100100

    Answer A in PrepSoc practice
  2. B

    200200

    Answer B in PrepSoc practice
  3. C

    300300

    Answer C in PrepSoc practice
  4. D

    400400

    Answer D in PrepSoc practice

Answer this questionOr tap an option. Opens in practice mode, free, no sign-in.

Show answer and solution

Answer: (A)

100100

Solution

  • Assume total work = LCM(10,8,410, 8, 4) = 4040 units:

    • Amal's rate = 4010=4 units/day\frac{40}{10} = 4\text{ units/day}

    • Bimal's rate = 408=5 units/day\frac{40}{8} = 5\text{ units/day}

    • Combined rate = 404=10 units/day\frac{40}{4} = 10\text{ units/day}

  • Kamal's rate:

    Kamal=10−(4+5)=1 unit/day\text{Kamal} = 10 - (4 + 5) = 1\text{ unit/day}

  • Proportional remuneration:

    • All three work together for all 44 days, so earnings split in ratio 4:5:14 : 5 : 1.

    • Kamal's share =14+5+1×1000=110×1000=100= \frac{1}{4 + 5 + 1} \times 1000 = \frac{1}{10} \times 1000 = \mathbf{100} (Option 1).

Detailed explanation

Concept: Time & Work / Proportional Wage Distribution via Individual Efficiency.

  1. When workers work together for the same duration to complete a project, the remuneration is shared in direct proportion to the amount of work completed by each individual.

  2. Determine the daily work rates:

    • Amal completes the job in 1010 days   ⟹  \implies Amal's daily rate =110= \frac{1}{10} of the job.

    • Bimal completes the job in 88 days   ⟹  \implies Bimal's daily rate =18= \frac{1}{8} of the job.

  3. Determine the combined daily work rate:

    • Amal, Bimal, and Kamal together complete the job in 44 days   ⟹  \implies Combined daily rate =14= \frac{1}{4} of the job.
  4. Calculate Kamal's individual daily rate:

    Kamal’s daily rate=14−(110+18)\text{Kamal's daily rate} = \frac{1}{4} - \left(\frac{1}{10} + \frac{1}{8}\right)

    • Taking the LCM of 4,10, and 84, 10, \text{ and } 8, which is 4040:

    Kamal’s daily rate=1040−(440+540)=10−940=140 of the job per day\text{Kamal's daily rate} = \frac{10}{40} - \left(\frac{4}{40} + \frac{5}{40}\right) = \frac{10 - 9}{40} = \frac{1}{40}\text{ of the job per day}

  5. Calculate the total fraction of work completed by each person over the 44 days:

    • Work done by Amal =4×110=410=1640= 4 \times \frac{1}{10} = \frac{4}{10} = \frac{16}{40}

    • Work done by Bimal =4×18=48=2040= 4 \times \frac{1}{8} = \frac{4}{8} = \frac{20}{40}

    • Work done by Kamal =4×140=440=110= 4 \times \frac{1}{40} = \frac{4}{40} = \frac{1}{10}

  6. Calculate Kamal's remuneration:

    Kamal’s share=Fraction of work done×Total remuneration\text{Kamal's share} = \text{Fraction of work done} \times \text{Total remuneration}

    Kamal’s share=110×Rs 1000=Rs 100\text{Kamal's share} = \frac{1}{10} \times \text{Rs } 1000 = \text{Rs } 100

Practise similar questions

Practice 1 CAT_2017_SLOT2_QA_Q13_SQ01

Anil can complete a project in 1212 days and Sunil can complete it in 1515 days. Anil, Sunil, and Vipul together complete the project in 55 days and are paid a total amount of Rs 36003600 as remuneration. If this amount is shared by them in proportion to their work, then Vipul's share, in rupees, is

  1. A

    750750

  2. B

    900900

  3. C

    10501050

  4. D

    12001200

Show answer and solution

Answer: (B)

900900

Solution

  • Let total work be LCM(12,15,5)=60\text{LCM}(12, 15, 5) = 60 units.

  • Anil's rate =6012=5= \frac{60}{12} = 5 units/day, Sunil's rate =6015=4= \frac{60}{15} = 4 units/day.

  • Combined rate =605=12= \frac{60}{5} = 12 units/day.

  • Vipul's rate =12−(5+4)=3= 12 - (5 + 4) = 3 units/day.

  • Since all work the full 55 days, earnings divide in ratio 5:4:35 : 4 : 3.

  • Vipul's share =312×3600=14×3600=900= \frac{3}{12} \times 3600 = \frac{1}{4} \times 3600 = \mathbf{900} (Option 2).

Practice 2 CAT_2017_SLOT2_QA_Q13_SQ02

David can complete an assignment in 66 days and Edward can complete it in 99 days. David, Edward, and Frank together complete the assignment in 33 days and are paid a total amount of Rs 30003000 as remuneration. If this amount is shared by them in proportion to their work, then Frank's share, in rupees, is

  1. A

    400400

  2. B

    500500

  3. C

    600600

  4. D

    750750

Show answer and solution

Answer: (B)

500500

Solution

  • Let total work be LCM(6,9,3)=18\text{LCM}(6, 9, 3) = 18 units.

  • David's rate =186=3= \frac{18}{6} = 3 units/day, Edward's rate =189=2= \frac{18}{9} = 2 units/day.

  • Combined rate =183=6= \frac{18}{3} = 6 units/day.

  • Frank's rate =6−(3+2)=1= 6 - (3 + 2) = 1 unit/day.

  • Ratio of daily work is 3:2:13 : 2 : 1.

  • Frank's share =13+2+1×3000=16×3000=500= \frac{1}{3 + 2 + 1} \times 3000 = \frac{1}{6} \times 3000 = \mathbf{500} (Option 2).

Time & Work questions from other CAT papers

  1. CAT 2025 Slot 1 Quant Q16
    Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They…
  2. CAT 2025 Slot 2 Quant Q10
    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start…
  3. CAT 2025 Slot 3 Quant Q7
    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a…
  4. CAT 2025 Slot 3 Quant Q13
    The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be…
  5. CAT 2024 Slot 1 Quant Q21
    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days…

Practise this question with timing, notes and your mistake notebook.

Practise in PrepSoc