CAT 2017 Slot 1 Quant Q2

  • Quantitative Aptitude
  • Arithmetic › Time & Work
  • Medium
  • Type in the answer (TITA)
  • CAT_2017_SLOT1_QA_Q02

Question 2

A person can complete a job in 120120 days. He works alone on Day 11. On Day 22, he is joined by another person who also can complete the job in exactly 120120 days. On Day 33, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job?

Type-in-the-answer (TITA) question: no options are given; enter the value.

Answer this question Opens in practice mode, free, no sign-in.

Show answer and solution

Answer:

15

Solution

  • Total work =120= 120 man-days.

  • Work done on day kk is kk man-days   ⟹  \implies Sum over nn days is n(n+1)2\frac{n(n+1)}{2}.

  • n(n+1)2=120  ⟹  n(n+1)=240\frac{n(n+1)}{2} = 120 \implies n(n+1) = 240.

  • Two consecutive integers multiplying to 240240: 15×16=240  ⟹  n=1515 \times 16 = 240 \implies n = 15 days.

Detailed explanation

Concept: Work-Rate Proportionality & Arithmetic Series Summation.

  1. Define work units:

    • Let the total work to be completed be W=120 unitsW = 120\text{ units}.

    • Since one person completes the job in 120120 days, the rate of one person is:

      r=120120=1 unit/dayr = \frac{120}{120} = 1\text{ unit/day}

  2. Tabulate daily work progress:

    • On Day 11: 11 worker   ⟹  1×1=1 unit\implies 1 \times 1 = 1\text{ unit}

    • On Day 22: 22 workers   ⟹  2×1=2 units\implies 2 \times 1 = 2\text{ units}

    • On Day 33: 33 workers   ⟹  3×1=3 units\implies 3 \times 1 = 3\text{ units}

    • On Day nn: nn workers   ⟹  n×1=n units\implies n \times 1 = n\text{ units}

  3. Formulate total work equation:

    • Total work completed in nn days is the sum of the first nn natural numbers:

      Total Work=∑k=1nk=n(n+1)2\text{Total Work} = \sum_{k=1}^n k = \frac{n(n+1)}{2}

  4. Solve for nn:

    • Equating total work to 120120 units:

      n(n+1)2=120\frac{n(n+1)}{2} = 120

      n(n+1)=240n(n+1) = 240

      n2+n−240=0n^2 + n - 240 = 0

    • Factor the quadratic equation:

      (n−15)(n+16)=0(n - 15)(n + 16) = 0

    • Since n>0n > 0, we have n=15n = 15.

  5. Therefore, exactly 1515 days are required to complete the job.

Practise similar questions

Practice 1 CAT_2017_SLOT1_QA_Q02_SQ01

A worker can complete a construction project in 5555 days. He works alone on Day 11. On Day 22, he is joined by another worker who also can complete the project in exactly 5555 days. On Day 33, they are joined by another worker of equal efficiency. Continuing in this manner, every day a new worker of identical efficiency joins the team. How many days are required to complete the project?

Type-in-the-answer (TITA) question: no options are given; enter the value.

Show answer and solution

Answer:

10

Solution

  • Total work =55= 55 man-days.

  • Work on day kk is kk man-days   ⟹  \implies Sum over nn days is n(n+1)2\frac{n(n+1)}{2}.

  • n(n+1)2=55  ⟹  n(n+1)=110\frac{n(n+1)}{2} = 55 \implies n(n+1) = 110.

  • Consecutive integers with product 110110: 10×11=110  ⟹  n=1010 \times 11 = 110 \implies n = 10 days.

Practice 2 CAT_2017_SLOT1_QA_Q02_SQ02

A painter can paint an entire gallery in 7878 days. He works alone on Day 11. On Day 22, he is joined by another painter of equal efficiency who can also complete the job in 7878 days. On Day 33, another painter of identical efficiency joins them. In this way, every day one additional painter with the same efficiency joins the group. How many days are needed to complete the painting job?

Type-in-the-answer (TITA) question: no options are given; enter the value.

Show answer and solution

Answer:

12

Solution

  • Total work =78= 78 painter-days.

  • Total work in nn days =n(n+1)2= \frac{n(n+1)}{2}.

  • n(n+1)2=78  ⟹  n(n+1)=156\frac{n(n+1)}{2} = 78 \implies n(n+1) = 156.

  • Consecutive integer product: 12×13=156  ⟹  n=1212 \times 13 = 156 \implies n = 12 days.

Time & Work questions from other CAT papers

  1. CAT 2025 Slot 1 Quant Q16
    Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They…
  2. CAT 2025 Slot 2 Quant Q10
    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start…
  3. CAT 2025 Slot 3 Quant Q7
    Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a…
  4. CAT 2025 Slot 3 Quant Q13
    The rate of water flow through three pipes A, B and C are in the ratio 4 : 9 : 36. An empty tank can be…
  5. CAT 2024 Slot 1 Quant Q21
    Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days…

Practise this question with timing, notes and your mistake notebook.

Practise in PrepSoc